Skip to content
NEPAL BUSINESS MONITORनेपाल बिजनेस मनिटर
DISASTER DESK · LIVEBhotekoshi floods: Rasuwagadhi still closed · A second flood in 14 months destroyed the border complex; temporary bridges planned, no reopening date.→

Power exports to Bangladesh resume after flood, using substitute plants

Solu Khola and Kabeli B1 replaced the flood-hit Trishuli and Chilime plants under the 40 MW deal.

Monitor Desk · ८ कात्तिक २०८३ · 1 min read
Power exports to Bangladesh resume after flood, using substitute plants
Photo: Saddam19 / Wikimedia Commons (CC BY-SA 4.0)

Nepal resumed its 40 MW electricity supply to Bangladesh through India's grid in late October, after the 26 August Bhotekoshi flood damaged the Trishuli and Chilime hydropower plants that had been feeding the deal. India's Central Electricity Authority approved Solu Khola and Kabeli B1 as replacements, Nepal Electricity Authority managing director Dirghayu Kumar Shrestha said.

The arrangement runs from 15 June to 15 November each year. Both governments have agreed to raise it to 60 MW, but the extra 20 MW has not materialised; India has cited transmission constraints.

Exports to India are far larger. Nepal exported Rs 16.15 billion of electricity in the first three months of the fiscal year, and India's approval of a further 31 MW took capacity cleared for export to India to about 1,179 MW. Nepal is seeking 10- to 15-year power trade approvals.